Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Equinor and Polenergia commenced geophysical seabed survey activities for the Bałtyk 3 (and sibling Bałtyk 2) export and inter-array cable corridors in December 2024 under a contract with DeepOcean. The flagship survey vessel Edda Flora was mobilised to perform the main scope of work, deploying a dedicated survey remotely operated vehicle (SROV) to map the seabed and finalise the cable-corridor design. The scope ran in parallel with the UXO sub-campaign delivered by Polish subcontractor MEWO S.A. using the vessel Amber Cecilia. These activities supported safe and efficient subsea cable installation, and were a prerequisite for the January 2026 start of subsea rock installation along the cable corridors.