Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Equinor and Polenergia awarded the Smulders–Sif consortium a contract to manufacture 100 transition pieces for the Bałtyk 2 and Bałtyk 3 offshore wind farms. These steel structures connect the monopile foundations to the turbine towers, with 50 units allocated to each project. The work includes fabrication of the complete transition‑piece structures with equipment, with part of the steelwork to be produced at Smulders’ facilities in Żory, Poland. This contract secures the secondary‑steel foundation components required to install the 50 Siemens Gamesa turbines planned for Bałtyk 3.