Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Tele‑Fonika Kable, a Polish cable manufacturer, was contracted to design, produce and deliver onshore export cables for the Bałtyk 2 and Bałtyk 3 offshore wind farms. For the two projects, Tele‑Fonika will supply approximately 85 km of 220 kV HV onshore export cables connecting the offshore substations to the onshore substations, and about 38 km of 400 kV EHV cables linking the onshore substations to the PSE Słupsk Wierzbięcino grid substation. All cables will be manufactured at the company’s Bydgoszcz plant before transport to the Polish coast for installation. This award designates Tele‑Fonika as the primary onshore high‑voltage cable supplier for Bałtyk 3.