Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 11 May 2026, Spie announced that its wind power high‑voltage specialist unit, Spie Wind Connect, had been awarded a contract by Seaway7 to perform termination and testing of 66 kV inter‑array cable systems on the Bałtyk II and Bałtyk III offshore wind farms. For Bałtyk 2, Spie Wind Connect will handle the electrical termination and commissioning tests of the inter‑array cables that link the Siemens Gamesa turbines to the offshore substations, working within Seaway7’s main cable installation scope. The main offshore campaign is expected to begin in the second quarter of 2026, with Spie’s activities supporting final grid connection and readiness of the array cabling system.