On 19 May 2025, in connection with the final investment decisions for Bałtyk 2 and Bałtyk 3, Equinor and Polenergia disclosed that they had already contracted several main Polish contractors for implementation of the projects, including Tele-Fonika Kable and Enprom. These awards cover key elements of the onshore and grid-related works and support the developers’ strategy to build a strong local supply chain around the Bałtyk projects. The contracts complement earlier awards for turbines, foundations, and offshore cables and mark further progress in locking in delivery capacity for Bałtyk 2 ahead of full-scale construction.