As part of cable and electrical infrastructure preparations for the Bałtyk II and Bałtyk III offshore wind farms, Equinor and Polenergia also signed a contract with DNV, announced on 25 October 2023. Under this agreement, DNV will certify the offshore parts of the projects, including Bałtyk 2’s offshore infrastructure. The certification scope covers conformity assessment of the design and construction of the offshore assets, supporting regulatory compliance and risk reduction for the twin 720 MW projects. This specialist certification award is an important procurement milestone complementing the main cable and electrical contracts.