Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 27 June 2025, Equinor and Polenergia confirmed that physical construction of the onshore infrastructure for the Bałtyk 2 and Bałtyk 3 offshore wind farms had started. Works include building two onshore power stations at Pęplin near Ustka, constructing the land-based sections of the export cable corridor, and developing a new operations and service base in Łeba. The article notes that construction has begun and that work is already in full swing on these elements, marking the transition of Bałtyk 2 (and its twin Bałtyk 3) into the onshore build phase that will enable connection of the 720 MW offshore project to Poland’s national grid.