Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 16 February 2024, Sif Holding NV confirmed that it had signed final contracts with the Equinor–Polenergia joint venture for the supply of 100 monopile foundations for the Bałtyk II and Bałtyk III offshore wind farms. For Bałtyk 2, Sif will fabricate monopiles at its Dutch facilities in Roermond and Rotterdam according to a schedule that starts manufacturing in the second quarter of 2025 and completes in the first quarter of 2026. The monopiles will support Siemens Gamesa SG 14‑236 DD turbines and be installed at sites approximately 37 km offshore. This contract secures the primary steel monopile supplier for Bałtyk 2 and locks in a key element of the foundation supply chain.