On 3 July 2024, Equinor and Polenergia announced that they had signed contracts with Heerema Marine Contractors for the transport and installation of foundations and offshore substations for the Bałtyk 2 and Bałtyk 3 offshore wind farms. For Bałtyk 2, Heerema will transport and install 100 monopiles and transition pieces, as well as the topsides of two offshore transformer stations, using heavy‑lift vessels including the crane ship Thialf. All foundations are planned to be installed in 2026, with substation topsides installed in separate campaigns in 2026 and 2027. This supply‑and‑install agreement secures the main offshore construction contractor for the foundation and OSS installation scope, a major EPCI milestone ahead of the 2026 offshore campaign.