Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
As of mid-December 2025 PGE Baltica reported that an initial geotechnical survey campaign for the Baltica 9 site (area 44.E.1) was underway and in its final stage, complementing the completed 2D UHRS geophysical surveys by Geofizyka Toruń. No exact start date is disclosed in the source pack; month-precision December 2025 is used here as the latest period in which the source explicitly confirms the survey is in progress. The geotechnical data supports foundation and cable design decisions for the subsequent procurement phase scheduled to commence in 2026.