Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Inferred CfD-award year for Baltica 7. Baltica 7 was not entered in Poland's first offshore wind CfD auction concluded 17 December 2025 (URE communique lists only Baltica 9 from PGE among bidders). Per WindEurope coverage of the auction outcome, "Poland's offshore wind roadmap includes further auctions in 2027, 2029, and 2031, each offering additional gigawatts of capacity." The Baltica 7 SPV (Elektrownia Wiatrowa Baltica-7 Sp. z o.o., area 43.E.1, ~990 MW) is being prepared for the 2027 second round. The CfD-eligibility decision (URE Art. 16/18 under Poland's Offshore Wind Promotion Act 2020) sets the project's strike price within the regulator's annually-published reference-price band. Year-precision projection pending the 2027 auction's exact scheduling by the Council of Ministers and URE; will be revisited after the auction outcome.