Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
PGE Group confirms that the Baltica-3 Wind Power Plant (Baltica 3) has secured its grid connection by entering into a transmission grid connection agreement with Polskie Sieci Elektroenergetyczne S.A. (PSE), Poland’s transmission system operator. The agreement, in place by 2020, defines the connection capacity and technical conditions under which up to 1,045 MW from Baltica 3 will be evacuated into the national power system. This marks a key regulatory and technical milestone for the project, complementing earlier steps such as location and environmental permits, and enabling further design and permitting stages that rely on a confirmed grid access point.