Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 26 September 2022, Baltic Power confirmed selection of a consortium of GE and ENPROM to deliver the onshore substation for the Baltic Power offshore wind project. Under the agreement, GE will design the electrical system and supply high‑voltage components, while ENPROM, one of Poland’s largest power construction firms, will be responsible for overall design and construction of the receiving station in the Choczewo municipality. This onshore substation will receive power from four offshore export cables and transform it for injection into the Polish transmission grid. The appointment of GE and ENPROM established the core delivery team for the onshore grid connection works ahead of the 2024 construction start.