Offshore construction for the Baltic Power offshore wind farm started in January 2025. The developer reports that the offshore installation campaign began that month, representing the first large-scale offshore wind construction operation in Polish waters. This campaign involves deploying a fleet of installation and support vessels to the 130 km² site approximately 23 km off the coasts of Łeba and Choczewo. Initial works focused on installing monopile foundations, with subsequent phases to add transition pieces, turbines, offshore substations and subsea cables.