Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Following an appeal against the 2021 regional environmental decision, the General Director for Environmental Protection (GDOŚ) conducted an appeal procedure and, on 29 June 2022, annulled the RDOŚ Gdańsk decision in full and issued a new environmental decision for the Morska Farma Wiatrowa Baltic Power project. This national-level DŚU, referenced under case DOO-WDZOO.420.59.2021.SP.10, redefined the environmental conditions for the project and replaced the earlier regional decision, becoming the binding basis for subsequent permitting and project implementation.