Northland Power Q1 2026 results dated 13 May 2026 — as-built status snapshot. Progress: monopile foundations 78/78 (completed Feb 2026); transition pieces 76/76 (completed Mar 2026); offshore substations 2/2 topsides installed (Oct 2025); export cables 4/4; inter-array cables all complete; WTGs 38/76 installed. This period (Q1 2026): completion of fabrication of remaining project components, installation of all four offshore export cables, installation of all inter-array cables, completion of all transition pieces, installation of 38 of 76 Vestas V236-15 MW turbines. Forecast: remaining 38 turbines installation to continue; commercial operations on track for the second half of 2026. Project costs reported as aligned with original expectations; approximately CAD 3 billion remained to be spent across Baltic Power and Hai Long combined as of the earnings call. Source: Northland Power Inc Q1 2026 results press release dated 13 May 2026, "on track for commercial operations in the second half of 2026" with "overall costs aligned with original expectations".