Low Impact
Minor progress or informational
By 19 March 2026, Baltic Power had completed installation of all 76 transition pieces that connect turbine foundations to the wind turbine towers. The project company, a joint venture between ORLEN Group and Northland Power, announced that every transition piece is now in place across the 130 km² site, approximately 23 km off the Polish coast near Łeba and Choczewo. These steel structures sit atop monopile foundations and provide the interface to the turbine towers. With this milestone reached, the project reports that installation of wind turbines as well as export and inter‑array cables is progressing at the offshore site. The completion of the transition piece campaign signifies that all primary structural links between foundations and turbines are ready ahead of full turbine installation and electrical outfitting.