Project advancing - milestone achieved
Low Impact
Minor progress or informational
On 26 September 2022, Baltic Power secured reservation contracts with its preferred cable suppliers for the Baltic Power offshore wind farm. NKT was selected to design and manufacture the 230 kV offshore export cable system, while TELE‑FONIKA Kable together with JDR Cable Systems were chosen to supply the inter‑array cables and the onshore section of the export circuits. In total, about 355 km of cables will be installed, including roughly 130 km of inter‑array cables linking turbines to offshore substations and export cables transmitting power to shore. TELE‑FONIKA Kable will also handle transport and installation of the onshore export cables, with DEME contracted for offshore cable transport and installation. These reservations locked in key suppliers ahead of final contracts and construction.