Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
During Q1 2026, Baltic Power completed installation of all four offshore export cables, marking completion of the offshore export cable installation campaign for the Baltic Power offshore wind farm. The export cables, supplied by NKT and installed by DEME Offshore under a consortium scope with NKT and TFKable, connect the project's two offshore substations to the landfall area near Lubiatowo and ultimately the new onshore substation in Choczewo. Northland Power's Q1 2026 results, dated 13 May 2026, confirm all four export cables were installed during the quarter alongside completion of all inter-array cables and 38 of 76 wind turbines. Completion of the export cable scope is a critical electrical milestone for the project, providing the export pathway from the offshore substations to the Polish transmission grid ahead of full commercial operations targeted for the second half of 2026.