Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
By October 2025, the Baltic East offshore wind farm had secured a permit for laying and maintaining submarine cables in Polish internal waters and the territorial sea (Pozwolenie na układanie i utrzymywanie kabli, PUUK). A linked article dated 10 October 2025 reports that Baltic East has obtained this PUUK, while the main Baltic East feature notes that the project already holds this cable permit alongside its siting decision (PSZW) and preliminary transmission grid connection terms. The PUUK covers the export and/or inter-array cable sections located within internal waters and the territorial sea and is a prerequisite for constructing and operating the project’s cable infrastructure along the route to shore.