Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
ORLEN Neptun appointed a Polish-led consortium of Ramboll (Polska), Projmors ASE Group and Enprom to deliver FEED and preliminary design works for the 900 MW Baltic East offshore wind farm, including technical documentation for building-permit applications. Scope split within the consortium: Ramboll Polska oversees overall project management, FEED design of the offshore components and detailed design of the wind turbine foundations; Projmors ASE Group leads the building-design effort and secures building permits for the offshore part; Enprom manages design and permitting of the onshore infrastructure (onshore export cable and onshore substation). The FEED package supports advancement of the project toward Final Investment Decision (planned 2029–2030) and the URE 7-year first-power deadline of 17 December 2032 under the AMFW/1/2025 CfD award. Reported by offshoreWIND.biz on 7 April 2026; the consortium selection was announced earlier in 2026.