Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
DELAYED +6mo (May 2026): Projected as starting by end-2024, but official Med floating wind update notes that for Golfe du Lion Centre (GLC) a new environmental baseline offshore campaign would start in spring 2025 for a two-year duration ("Une nouvelle campagne démarrera au printemps 2025 pour la zone GLC"). This better matches the 'other surveys/environmental state' milestone timing than end-2024. --- Following the October 2024 maritime planning decision, the State announced that offshore studies would be carried out from autumn 2024 in the newly defined Golfe du Lion priority zones, including Golfe du Lion Centre, to support offshore wind development and biodiversity protection ahead of the AO10 tender.