Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
The AO10 Mediterranean government briefing deck (Direction interrégionale de la mer Méditerranée, commission spécialisée éolien flottant, 21 Feb 2025) includes a “Concertation” timeline showing for the 2 GW AO10 project: “PPVE (ou enquête publique)” occurring during 2027–2028 (after earlier State/RTE concertation in 2025–2026 and before the 2029–2035 period). This indicates the statutory public participation / inquiry stage of the permitting process is planned to run in 2027–2028, implying the project-level authorisation decision would be expected after that stage; projecting planning consent awarded by end-2028 consistent with this stated permitting schedule (without asserting a specific decision date).