Special-purpose vehicle holding the IJmuiden Ver Beta Phase 2 permit obligations under the Wijzigingsbesluit of 6 August 2025 (Staatscourant 2025, 28710), which split the original 2 GW Zeevonk permit into Phase 1 CV and Phase 2 CV. Phase 2 CV holds the 1 GW second-tranche delivery (operational by 30 November 2032) and the 500 MW system-integration / hydrogen-facility obligation. Owned 50/50 by Vattenfall and Copenhagen Infrastructure Partners (Energy Transition Fund I).